What is a BOQ (bill of quantities)?

A BOQ, or bill of quantities, lists every item of work in a building with its quantity and unit, grouped into sections such as Sub-structure, Masonry and Finishes. A Priced BOQ adds a rate and an amount to every item. In Vextrus, each quantity is the sum of its Measurement Lines, traced to its line on the drawing.

Published Updated 5 min read
One column selected inside the Live Model of the Demo building, the Building drawn as glass around it: one of the Elements a BOQ's quantities are measured from.

What does BOQ stand for?

BOQ stands for bill of quantities. In construction and civil engineering it is the document that turns a building’s drawings into a list of work that can be priced: every item described, measured in its unit and grouped by the part of the building it belongs to. Priced, it is the figure a Developer builds, buys and pays against.

A BOQ is written for one building. A Developer’s QS prepares it from the consultants’ drawings. In a tender, the same list goes to every bidder, who prices it item by item, so every bid prices the same items.

What is in a BOQ?

Every BOQ Item has a description, a unit and a quantity. The description names the work and, where it matters, its Mix and grade: RCC 1:1.5:3 in columns, 10-inch brickwork, cement plaster to walls. A Priced BOQ adds the rate per unit and the amount, which is the quantity times the rate.

The units follow the way the work is measured and paid. In Bangladesh that means cft for RCC and 10-inch brickwork, sft for 5-inch brickwork and plaster, rft for running lengths, nos for counted items, kg and ton for Rebar, bag for cement and LS for a Lump Sum. Vextrus uses these by default, with metric one switch away.

Items are grouped into BOQ Sections. Vextrus uses seven, in building order: Sub-structure, Super-structure, Masonry, Finishes, Doors & Windows, Services and External works. The same items can also be read by Trade: concrete, formwork, Rebar work, brickwork, plaster and the rest. Lump Sum and Provisional Sum items stay outside the measured subtotal.

What is a BOQ used for?

A BOQ is used to price a building, to buy for it, to let its work and to pay for it. The priced items add up to the cost. The same quantities tell procurement what to buy, give each labour contractor a measured scope, and are the measure a running bill is checked against.

In Vextrus each of those jobs reads the same quantities. The Material Schedule, the cement, sand, stone chips, Rebar by diameter and bricks to buy, by floor and by Construction Stage, comes from the same takeoff as the Priced BOQ. In Cost (5D), a running bill is checked against the Elements that support its claim. See what the BOQ means for procurement.

Who prepares a BOQ?

A QS prepares the BOQ: the quantity surveyor or estimation engineer, at the Developer or working for it, who measures quantities from drawings and prices them. The QS measures each item from the sheets, writes the measurement sheets, builds each rate from its Resources and prices the whole bill. Read what a QS does, or see Vextrus for the QS.

How does a quantity become an amount?

A quantity becomes an amount in three steps. The QS measures the item’s lines from the drawing, No. × L × B × H with the deductions named; the lines add up to the item’s quantity in its unit; and that quantity, times the rate from the item’s Rate Analysis, gives the amount.

In Vextrus each quantity is rounded in its unit, as the Rule Set sets it, and the amount is that printed quantity times the rate, exactly, so every BOQ Item cross-checks by hand. The rate comes from a Rate Analysis at the Developer’s own Market Prices. Two articles go further: how a rate is built from its Resources and how a BOQ is prepared from 2D drawings.

The Measurement Sheet

A synthetic example: the slabs of the plan

RCC 1:1.5:3 in suspended floor slab, 5" thick (cft)

The Measurement Sheet: A synthetic example: the slabs of the plan. RCC 1:1.5:3 in suspended floor slab, 5" thick (cft)
ElementNosLBHQuantity (cft)
Slab panel S14-5/A-B, 4-5/C-D214'-6"11'-9"0'-5"141.98
Slab panel S22-3/A-B, 2-3/C-D, 3-4/A-B, 3-4/C-D413'-6"11'-9"0'-5"264.38
Slab panel S31-2/A-B, 1-2/C-D, 5-6/A-B, 5-6/C-D412'-0"11'-9"0'-5"235.00
Slab panel S42-3/B-C113'-6"15'-0"0'-5"84.38
Slab panel S51-2/B-C, 5-6/B-C212'-0"15'-0"0'-5"150.00
Slab panel S64-5/B-C114'-6"15'-0"0'-5"90.63
Stair and lift core: no slab (measured with the stair)3-4/B-C0.00
Total966.37
Slab panels grid to grid; every beam measured below the slab; the perimeter beams’ outer half, outside the grid line, full depth; the stair and lift core left out.

Is a BOQ the same as an estimate?

No. The Priced BOQ is the bill of quantities for a building, item by item by trade, with a rate and an amount on every item. The Estimate is the total cost of a Project: the Priced BOQ’s direct cost plus preliminaries and site overheads, contingency and taxes, each layer shown and editable by the Developer.

In everyday speech the whole document is often called the estimate. Vextrus keeps the two words apart because they do different jobs. When the Estimate is issued, by a person’s Signature, Vextrus freezes the Priced BOQ, the Material Schedule, the Market Prices, the Rule Set version and the Live Model’s state into an Issued Estimate with an issue number and date. That is the figure the MD takes to the board, and later changes are compared against it.

What does a Priced BOQ in Vextrus add?

A Priced BOQ in Vextrus adds the Trace: every quantity, rate and amount opens where it came from. Click a figure and a drawer lists its Elements with their storey, grid place and sheet, and its Measurement Lines as a measurement sheet. From the MD’s number to its own line, lit on the sheet, is three clicks.

The cells are live-linked to the takeoff. Beside each working rate stands the Benchmark Rate, the PWD Schedule of Rates rate as printed and net of PWD’s mark-ups; a gap between them is a question the QS answers, labour included. A Market Price is the one place a price changes, so every working rate and amount follows. The Priced BOQ exports to Excel with live formulas, to CSV and as a PWD-style print, and its columns are added and removed as in Excel, so no Developer is locked into one format. See the Priced BOQ in Vextrus.

The words on this page are defined in the Vextrus glossary, with Estimate and BOQ Item beside it. See every article on the Learn page.

Questions

What is the full form of BOQ?

BOQ is short for bill of quantities: the list of every item of work in a building with its quantity and unit, grouped into sections. With a rate and an amount on every item, it is a Priced BOQ. In Vextrus each quantity is the sum of its Measurement Lines, traced to its line on the drawing.

What is a BOQ Item?

A BOQ Item is one line of the Priced BOQ: a description with its Mix, grade and kind of Element, a unit, a BOQ Section and a Trade. Its quantity is the sum of its Measurement Lines, and its rate comes from its Rate Analysis. In Vextrus every BOQ Item opens the Elements and the drawing lines behind it.

What are a Lump Sum and a Provisional Sum in a BOQ?

A Lump Sum is a BOQ Item priced as one typed amount, with the unit LS and no Rate Analysis, such as a utility connection charge. A Provisional Sum is an amount set aside for work whose scope is still open. In Vextrus both count toward the Estimate and both stay outside the measured subtotal.

Send us a drawing set. See every number traced.

Drawn once. Every number traced.