Schedule (4D): the building rises, pour by pour

What is Schedule (4D) in Vextrus?

Schedule (4D) in Vextrus puts dated Activities on the Elements of the Live Model, with pours as the spine, so the Building rises as the date moves. Construction Stages keep their order, overlapping where the work allows. Each pour shows the Hold Points still open and waits for a signed Pour Release.

The Building in the Live Model, its pours changing colour one by one in the order they are cast.

What you do

The Planner generates the plan over the Project calendar. Read the Gantt and its critical path, the chain of Activities that sets the finish date; drag the as-of slider to watch the Building rise pour by pour; open a pour to see the Hold Points still open and its Pour Release.

Schedule (4D) · Gantt by Construction Stage

Synthetic example, not to time

The Activities of a synthetic Ground + 6 building by Construction Stage, as of the 4th floor slab, the next pour
Construction StageState
PilingPilingdone, on the critical path
SubstructureSubstructuredone, on the critical path
1st floor slab casting1st floor slabcast, on the critical path
2nd floor slab casting2nd floor slabcast, on the critical path
3rd floor slab casting3rd floor slabcast, on the critical path
4th floor slab casting4th floor slabthe next pour, on the critical path
5th floor slab casting5th floor slabplanned, on the critical path
6th floor slab casting6th floor slabplanned, on the critical path
Roof slab castingRoof slabplanned, on the critical path
MasonryMasonryin progress
ServicesServicesplanned
FinishesFinishesplanned, on the critical path
External worksExternal worksplanned
  • Critical path
  • Other Activities
  • Done by the as-of date

Each floor's columns are poured before its slab.

Next pour · 4th floor slab

Hold Points2 still open

Pour Releasewaits for an engineer's Signature

A synthetic example: a Gantt in Vextrus by Construction Stage beside the Ground + 6 building it plans, drawn as of a date, the pours as the spine and the critical path marked, and the next pour’s card with its Hold Points still open and the Pour Release waiting for an engineer’s Signature.

What changes

You know which pour is not ready before the concrete is booked: each pour shows the Hold Points still open and waits for a signed Pour Release.

42% late

Next door in India, 779 of 1,873 central-government projects were running late.

Source: Government of India, MoSPI, monthly summary to Cabinet, May 2024 · India, central-government projects, March 2024

How it works

  1. The Planner generates the plan over the Project calendar: dated Activities, each on a set of Elements.

  2. Pours are the spine: the plan is built around each pour of concrete. Construction Stages (piling, substructure, each floor’s slab casting, masonry, services, finishes, external works) keep their order, overlapping where the work allows.

  3. The Gantt shows the critical path, the chain of Activities where any one running late moves the finish date; click a bar and its Elements light in the Live Model.

  4. Drag the as-of slider: the Building rises, pour by pour, to that date.

  5. Each pour carries its Hold Points, the conditions it must clear before concrete is placed, and shows which are still open.

  6. The pour waits for its Pour Release: an engineer’s Signature, a person’s act, never automatic.

  7. Each Construction Stage shows its Element count, and team roles see its ৳; Buyers see progress only.

Who uses it

Team roles see ৳ by Construction Stage. Buyers see progress only, never ৳. The Planner generates the plan; others read it.

Questions

What is 4D scheduling in construction?

4D scheduling joins a building's model to its programme, so every date shows what is built by then. In Vextrus, Schedule (4D) puts dated Activities on the Elements of the Live Model, the same Elements the Priced BOQ and Cost (5D) read, so the plan, the quantities and the cost by stage come from one model.

What is the critical path?

The critical path is the chain of Activities with no slack: if any one of them finishes late, the whole job finishes late. In Vextrus the Gantt shows the critical path, and clicking a bar lights the Elements its Activity works on in the Live Model.

What is a Hold Point before a pour?

A Hold Point is a condition a pour must clear before concrete is placed. In Vextrus each pour in the Schedule (4D) carries its Hold Points and shows which are still open, so the team sees which pour is not ready before the concrete is booked. The pour waits for a signed Pour Release.

Who signs the Pour Release?

An engineer, with a Signature: a person's act, never automatic, and enabled only for the assigned signer. Until it is signed, the pour shows its Hold Points and which of them are still open.

Who makes the plan in Vextrus?

The Planner generates the plan over the Project calendar, and the other roles read it. Each Activity sits on the Elements it works on, so when a Revision touches those Elements, the plan shows "Revision pending" until the QS confirms the change.

What can Buyers see of the schedule?

Progress only. A Buyer, invited as a Guest, sees the Construction Stages in order, planned and actual dates, the handover date and progress per stage on the Live Model, and never ৳ or another Buyer's data.