The site engineer and the site team
Vextrus gives the Site Engineer and the site team the same Live Model the head office reads.
Vextrus gives Procurement and the store each pour’s needs from the Material Schedule, derived from the same takeoff as the Priced BOQ. Procurement raises a requisition, sends an RFQ to dealers by link and ranks the quotes by landed cost; the order it accepts goes out inside the MD’s Standing Authority, or waits for the MD’s Signature.

49% manually; 44% by spreadsheet (multiple answers)
2020, mostly North America: when their apps don't integrate, 49% of respondents move data manually, 44% by spreadsheet.
Material Schedule
A synthetic example: one floor's slabs
RCC 1:1.5:3, 966.37 cft from the slab sheet; dry volume 1.5 times the wet, in 5.5 parts
| Resource | Share | Quantity |
|---|---|---|
| Cement263.56 cft, at 1.25 cft a bag | 1 part | 210.84 bags |
| Sand | 1.5 parts | 395.33 cft |
| Stone chips | 3 parts | 790.67 cft |
Team roles see ৳ in Materials. The MD signs any order outside the Standing Authority. Materials is closed to Guests.
A BOQ, the bill of quantities, lists every item of work with its quantity, and materials are bought against it. In Vextrus, Procurement reads the Material Schedule, derived from the same takeoff as the Priced BOQ: the basic materials by floor and by Construction Stage, with Wastage added to what is bought, while every BOQ quantity stays measured net.
For 12 m bars, at d²/162 kg a metre: 10 mm, 7.41 kg a bar, about 135 a ton; 12 mm, 10.67 kg, about 94; 16 mm, 18.96 kg, about 53; 20 mm, 29.63 kg, about 34; 25 mm, 46.30 kg, about 22. Actual weights vary with the mill’s tolerance. In Vextrus the Material Schedule gives Rebar by diameter, in ton.
From the Material Schedule. In Vextrus each pour’s needs show by Resource, Construction Stage and week, with Rebar by diameter, derived from the same takeoff as the Priced BOQ, and a cell lights the Elements it is for in the Live Model. Procurement drafts those needs into a requisition.
Because quotes differ in what they include. Vextrus ranks every quote on a requisition by landed cost, the price delivered to site, so the lowest quoted price can rank second. The quote Procurement accepts raises the Purchase Order, inside the MD’s Standing Authority or for the MD’s Signature.
Drawn once. Every number traced.