What does Vextrus change for procurement and the store?

Vextrus gives Procurement and the store each pour’s needs from the Material Schedule, derived from the same takeoff as the Priced BOQ. Procurement raises a requisition, sends an RFQ to dealers by link and ranks the quotes by landed cost; the order it accepts goes out inside the MD’s Standing Authority, or waits for the MD’s Signature.

The top slab of the Building poured in the Live Model, then released: one pour, whose needs Procurement buys.

Today

  • Each pour’s needs have to be bought in time, Resource by Resource and week by week.
  • Dealers’ quotes have to be compared on landed cost, not on price alone.
  • When a Revision changes a member’s bars, what has to be bought changes with it.
  • Everything is disconnected: needs, quotes and orders sit in chat messages and Excel.

49% manually; 44% by spreadsheet (multiple answers)

2020, mostly North America: when their apps don't integrate, 49% of respondents move data manually, 44% by spreadsheet.

Source: JBKnowledge with Texas A&M University, 2020 ConTech Report (9th Annual Construction Technology Report), 2020 · volunteer survey, self-reported; mostly North American construction firms; multiple answers allowed

What changes

  1. Materials

    • The Material Schedule gives the cement, sand, stone chips, Rebar by diameter and bricks the Building needs, by floor and by Construction Stage, derived from the same takeoff as the Priced BOQ.
    • Needs show by Resource, Construction Stage and week, and a cell lights its Elements in the Live Model, so the next pour’s needs are read from the building, not phoned in.
    • A requisition goes out as an RFQ to dealers by link, and every quote is ranked by landed cost, the price delivered to site, not the price on the quote.
    • Quotes are ranked by landed cost; the order Procurement accepts raises the Purchase Order, inside the Standing Authority or for the MD’s Signature.

    Material Schedule

    A synthetic example: one floor's slabs

    RCC 1:1.5:3, 966.37 cft from the slab sheet; dry volume 1.5 times the wet, in 5.5 parts

    Material Schedule, a synthetic example: one floor's slabs, 966.37 cubic feet of RCC 1:1.5:3, as materials before Wastage
    ResourceShareQuantity
    Cement263.56 cft, at 1.25 cft a bag1 part210.84 bags
    Sand1.5 parts395.33 cft
    Stone chips3 parts790.67 cft
    Before Wastage: the Material Schedule adds Wastage to what is bought, and the BOQ quantity stays measured net. Rebar comes by diameter from the signed bar bending schedule.
  2. Rebar

    • Procurement orders Rebar from the BBS the Structural Engineer signed. When a Revision changes a beam or a column, its BBS shows as Stale before anyone buys.
  3. Revision

    • Every module, Materials included, shows Revision pending until the QS confirms a Revision, and the changed Elements light in 3D.

Who sees money

Team roles see ৳ in Materials. The MD signs any order outside the Standing Authority. Materials is closed to Guests.

Questions

What is a BOQ in procurement?

A BOQ, the bill of quantities, lists every item of work with its quantity, and materials are bought against it. In Vextrus, Procurement reads the Material Schedule, derived from the same takeoff as the Priced BOQ: the basic materials by floor and by Construction Stage, with Wastage added to what is bought, while every BOQ quantity stays measured net.

How many pieces of Rebar are in a ton?

For 12 m bars, at d²/162 kg a metre: 10 mm, 7.41 kg a bar, about 135 a ton; 12 mm, 10.67 kg, about 94; 16 mm, 18.96 kg, about 53; 20 mm, 29.63 kg, about 34; 25 mm, 46.30 kg, about 22. Actual weights vary with the mill’s tolerance. In Vextrus the Material Schedule gives Rebar by diameter, in ton.

How does the store know what the next pour needs?

From the Material Schedule. In Vextrus each pour’s needs show by Resource, Construction Stage and week, with Rebar by diameter, derived from the same takeoff as the Priced BOQ, and a cell lights the Elements it is for in the Live Model. Procurement drafts those needs into a requisition.

Why is the cheapest quote not always the best price?

Because quotes differ in what they include. Vextrus ranks every quote on a requisition by landed cost, the price delivered to site, so the lowest quoted price can rank second. The quote Procurement accepts raises the Purchase Order, inside the MD’s Standing Authority or for the MD’s Signature.