Cost (5D): certify what is built

What is Cost (5D) in Vextrus?

Cost (5D) in Vextrus reads the Building's money from the Live Model. The Budget is cut from the Issued Estimate by Storey Band (a range of floors) and Construction Stage; each Running Account bill is checked against the Elements built and certified with a Signature; Revisions are priced as Variations; cash and Earned Value come from the same model.

One floor's slab panels in the Live Model: the panels recorded as built, and the panels a Running Account bill claims beyond them.

What you do

Open a Budget cell to its Measurement Lines, check a Running Account bill's claim against the Elements that support it and certify it with a Signature, price a Revision as a Variation, and see the cash trough, the point where the Project's cash runs lowest, move with the plan.

Running Account bill 7 · Labour Contract

Demo building · a demonstration project

Running Account bill 7: each claim line read against the Elements built
Claim lineBOQ ItemClaimedSupported by the Elements built
L1 4th floor slab and beams: casting2.6.1100 %in full
L2 4th floor slab formwork2.3.2100 %in full
L3 5th floor columns and walls: casting2.6.1100 %in full
L4 5th floor columns and walls: formwork2.1.3100 %in full
L5 5th floor slab formwork2,038.17 sft2.3.2100 %61 %
L6 5th floor beam formwork2.2.2100 %in full

L5 · 5th floor slab formwork · BOQ Item 2.3.2 at ৳20 a sft

claimed 100 % · 2,038.17 sft

built 61 % · 1,240.99 sft (by formwork area)

Claimed
2,038.17 sft × ৳20 = ৳40,763.40
Certified
1,240.99 sft × ৳20 = ৳24,819.80
Not certified
(2,038.17 − 1,240.99) sft = 797.18 sft × ৳20 = ৳15,943.60

L1 to L4 and L6: claimed 100 %, supported in full

Supported amount certified with a Signature

A Running Account bill in Vextrus for the Demo building: each claim line read against the Elements built, one claim beyond them, and the supported amount certified with a Signature.

What changes

You certify what is built: a claim is certified only up to what the Building shows, and a person signs it.

+58%

In a 186-project sample, buildings averaged 58% over budget in real terms.

Source: Flyvbjerg, Budzier & Christodoulou, arXiv 2606.15757 (preprint), 2026 · 186 building projects; preprint

How it works

  1. The Estimate is issued with a Signature and frozen as an Issued Estimate. The Budget is cut from that Issued Estimate by Storey Band and Construction Stage, and names the Issued Estimate it came from.

  2. A Budget cell opens to its Measurement Lines, and each line to the Element it measures and its line on the drawing.

  3. On site, the Site Engineer records what is built on each Element: a named person’s record.

  4. Each Running Account bill is read against the Live Model line by line; a claim beyond what the Elements built support is shown with its gap.

  5. The MD or the QS certifies the supported amount with a Signature. A second Signature applies only where the Developer’s own policy sets one; there is no default.

  6. A Revision is priced as a Variation, from the Elements it changes, and no money moves across it until the QS confirms it.

  7. Cash and Earned Value are read from the same model: the cash trough moves with the plan, and the work planned is set against the work done.

Who uses it

Team roles see ৳ in Cost (5D). The MD and the QS sign. Cost (5D) is closed to Guests.

Questions

What is 5D in construction?

5D adds cost to a building's model and its schedule, so the money is read from the same Elements as the quantities and the dates. In Vextrus, Cost (5D) reads the Live Model: the Budget from the Issued Estimate, bills against the Elements built, Variations from Revisions, and cash and Earned Value.

What does it cost to build a 6-storey building?

Your building's cost comes from its own drawings, priced at your own Market Prices, not from a typical rate per square foot. In Vextrus the QS confirms every quantity measured from the drawings, the Priced BOQ prices it, and Cost (5D) then tracks the money against the Issued Estimate as the building is built.

What is a Running Account bill?

A Running Account bill is a contractor's interim bill for the work done to date. In Vextrus each claim line is checked against the Elements built that support it, and only the supported amount is certified, with a Signature by the MD or the QS.

How does Vextrus know what is built?

From the Site Engineer's records. A named person on site records each Element's state as the work is done, and Cost (5D) reads those records: a bill's claim is checked against the Elements recorded as built, and only what they support is certified.

What is Earned Value?

Earned Value is the Budget's value of the work actually done, set against the value of the work planned by the same date. In Vextrus, Cost (5D) reads both from the Elements of the Live Model and the plan, so the MD sees the work planned and the work earned side by side.

What is a Variation?

A Variation is a change to the work and its price. In Vextrus, when a Revision of the drawings changes Elements, Cost (5D) prices the change as a Variation, traced to the Elements that changed, and no money moves across the Revision until the QS confirms it.

Send us a drawing set. See every number traced.

Drawn once. Every number traced.