How Vextrus works, from the Drawing Set to the building’s whole life
Vextrus is the Drawing-to-Handover platform for real-estate Developers: it reads a Developer’s whole 2D Drawing Set once into one confirmed Live Model, and the Priced BOQ, the site, cost and handover all read that one model, every figure traced to its line on the drawing.

How does Vextrus turn 2D drawings into a BOQ?
Vextrus turns a Developer’s 2D drawings into a bill of quantities through its quantity takeoff, the Takeoff. The QS uploads the whole Drawing Set once, the machine drafts every Element, and the QS confirms the draft by exception into one Live Model. The Priced BOQ is read from that model, every quantity traced to its line on the drawing.
Read how to prepare a BOQ from 2D drawings · Read what quantity takeoff is
One workflow, two ways in
Your QS runs the Takeoff on Vextrus. Or, without a QS team, you send us the Drawing Set, and our own QSs run it on the same Takeoff Workbench, held to the same safeguards and measured the same way. See the done-for-you service.
The steps below are the same both ways. Each one names who acts, and where the service changes who acts, the step says so.
Send the Drawing Set
01 Send us a drawing set.
Who: the MD or the QS.
The Developer sends the whole Drawing Set as its consultants issue it, or its QS uploads it, and we answer with a fixed quote for the Building. Under the service, our QSs take the Takeoff from there. See what happens after you send a drawing set.
02 The Developer’s space opens.
Who: the MD.
It is the Developer’s own space, closed to every other Developer; its people are invited by name with their roles, and who sees money is set per role. A Vextrus Engineer works in it by its time-bound invitation, and every opening is recorded where the MD sees it. Learning from the set needs the Developer’s consent. See the Project hub.
Read the whole set once
03 Upload the whole set once.
Who: the QS (ours, under the service).
Vextrus stores each file, sorts the set by Discipline and reads Structural first, then Architectural with it, then MEP and fire. The QS sees each file’s Discipline and can fix a sort.
04 Every sheet accounted for.
Who: the QS (ours, under the service).
The Drawing List is checked both ways against the consultant’s list. Coverage marks every view on every sheet as used, assigned or excluded with a reason, so nothing is silently unread. A missing Discipline is a Question, never zero.
05 Confirm the set’s conventions.
Who: the QS (ours, under the service).
A few one-click convention cards, each found in the set’s own drawings and shown with its drawing crop, its meaning and the Elements and ৳ that ride on it. The QS confirms a card, overrides that one item, or sends it to the RFI list. Every set is read on its own conventions.
06 Notes, storeys, levels and grid are read.
Who: the machine.
A level that disagrees between sheets, or a sheet that does not line up with the others, becomes an exception, and a height inferred from levels says so.
07 The machine drafts the whole model.
Who: the machine.
Every Element Family in building order, each Element with its Trace and its Measurement Lines. The draft counts toward nothing until the QS confirms it. See how the AI proposes and code measures.
Convention card
Synthetic plan
Its meaning
“this layer holds the columns”
Rides on it
The 24 columns of this plan
Confirm it by exception
08 Review by exception, type by type.
Who: the QS (ours, under the service).
The types run in building order, the order of the Takeoff Steps: grid and storeys, piles, caps, tie beams, columns, shear walls and core, beams, slabs, then stairs and tanks, walls and openings, rooms and finishes, the roof and site works, then each MEP Discipline. Each type, wall runs, openings and rooms included, takes four steps:
- The cross-checks first, before the Proposals.
- Then a blind spot-measure: the QS measures two or three random items of the type by hand.
- Then the exception groups, largest quantity first. Fix one Element and Vextrus offers the same fix to every similar Element, on the sheet and across storeys, with the matching rule and the count; one act applies it, revertible, never silently. An opening’s deduction from its wall follows the Rule Set’s Measurement Rule and is named on the wall’s measurement sheet.
- Then accept the type. Every act is a Confirmation in the Journal.
09 Rule once per issue type; route the rest.
Who: the QS (ours, under the service).
One ruling settles a whole group of exceptions. Items only the consultant can answer go to the RFI list, one Thread per item, with a provisional value labelled inferred until the answer comes. Notes that name no Element go to the assumptions-and-gaps report. No Estimate is issued with an unresolved exception.
10 The Live Model is the confirmed set.
Who: the machine.
Solids for confirmed Elements only; each keeps its basis and, beside it, who confirmed it and when. This is the Live Model every module reads, every figure with its Trace.

Four safeguards, all required
People follow wrong machine suggestions, experts included, and training does not stop it. So the safeguards are in the screen, and the QS cannot skip them.
- Cross-checks before Proposals. The schedule against the plan, typical-floor repetition, kg of Rebar per unit volume of concrete, area ratios.
- An active spot-measure. The QS measures two or three random items of each type by hand, blind. A difference beyond the type’s tolerance holds the type and draws two or three more; a second miss opens the whole type to one-by-one review.
- No blind bulk-accept. A type’s accept button is enabled only when its checks pass, the Trace has been opened, the spot-measure has matched, every exception group is settled and the unclaimed geometry examined. The button names its count and quantities.
- A dedicated review mode, separate from pricing and Revisions.
The review mode · Slab panels
Synthetic plan
The cross-checks
- The schedule against the plan
- Typical-floor repetition
- kg of Rebar per unit volume of concrete
- Area ratios
The spot-measure, blind
- S2, S4, S6: measured by hand, matched
The exception groups, largest quantity first
- S3, 4 panels, 235.00 cft: edge off its grid, settled
- S6, 1 panel, 90.63 cft: thickness differs from the schedule, settled
Before the accept
- The Trace opened
- The unclaimed geometry examined
Accept the type: 14 slab panels, 966.37 cft
Price the BOQ from the drawings
11 Rebar.
Who: the QS reads the bars; the Structural Engineer signs the BBS.
The Estimate’s Rebar figure carries its Rebar Basis: by ratio, from a Rebar Ratio and labelled so, until the bars are read. Then the bars are read from the drawing’s callouts, each figure with its own Rebar Basis; laps, hooks and anchorage are worked by rule where the drawing is silent; every bar on the BBS is checked against BNBC 2020. Once the BBS is signed, a later edit marks it stale. The BBS read from the callouts and signed comes with the On site package. See Rebar.
12 The Priced BOQ is priced.
Who: the QS (ours, under the service).
Each quantity is the sum of its Measurement Lines. Each rate comes from its Rate Analysis at the Developer’s Market Prices, and beside it stands the PWD Schedule of Rates rate, as printed and net of PWD’s mark-ups; a gap between them is a question the QS answers, labour included. The BOQ is never totalled on the PWD rate. Every Discipline is in the Priced BOQ from its own drawings, never as an allowance: electrical by the Point, plumbing and fire fixtures and equipment counted, runs priced by rule per point and per fixture, the rule named and kept as a visible Rule Set parameter the QS sees and the Developer can change. Cells stay live-linked to the takeoff. See the Priced BOQ.
13 The Estimate is issued.
Who: the QS; under the service, a named Vextrus QS signs it, and your MD or engineer accepts it, with the measurement sheets, Traces, RFI list and assumptions-and-gaps report to check it by.
The Estimate is issued by a person’s Signature, never automatically, and frozen as an Issued Estimate: the Priced BOQ, the Material Schedule, the Market Prices, the Rule Set version and the Live Model’s state.
14 The MD reads it.
Who: the MD.
The Project Summary shows the Estimate against the Target Cost, the cash runway and the float to the next bank milestone, every figure with its Trace. The Issued Estimate is the figure the MD takes to the board, with a Board Pack frozen as issued. See the Project Summary.
The Measurement Sheet
A synthetic example: the slabs of the plan
RCC 1:1.5:3 in suspended floor slab, 5" thick (cft)
| Element | Nos | L | B | H | Quantity (cft) |
|---|---|---|---|---|---|
| Slab panel S14-5/A-B, 4-5/C-D | 2 | 14'-6" | 11'-9" | 0'-5" | 141.98 |
| Slab panel S22-3/A-B, 2-3/C-D, 3-4/A-B, 3-4/C-D | 4 | 13'-6" | 11'-9" | 0'-5" | 264.38 |
| Slab panel S31-2/A-B, 1-2/C-D, 5-6/A-B, 5-6/C-D | 4 | 12'-0" | 11'-9" | 0'-5" | 235.00 |
| Slab panel S42-3/B-C | 1 | 13'-6" | 15'-0" | 0'-5" | 84.38 |
| Slab panel S51-2/B-C, 5-6/B-C | 2 | 12'-0" | 15'-0" | 0'-5" | 150.00 |
| Slab panel S64-5/B-C | 1 | 14'-6" | 15'-0" | 0'-5" | 90.63 |
| Stair and lift core: no slab (measured with the stair)3-4/B-C | 0.00 | ||||
| Total | 966.37 | ||||
Build from the same model
Planning, buying, the site and cost all read the Live Model the Estimate was issued from.


15 The Budget is cut.
Who: the QS and the MD.
From the Issued Estimate, by Storey Band and Construction Stage. See Cost (5D).
16 The plan is generated.
Who: the Planner.
Activities on Elements, pours as the spine, Construction Stages in their order, overlapping where the work allows: the Building rises in 4D by date. See Schedule (4D).
17 Materials are bought.
Who: Procurement; the MD signs any order outside the Standing Authority, the MD’s own buying limit.
Needs, a requisition, an RFQ, the lowest landed cost, then a Purchase Order: inside the Standing Authority it goes out, and outside it the MD signs. See Materials.
18 The team works on the model.
Who: the team roles; the MD signs.
Threads pinned to Elements and sheet regions close as signed Resolutions, and the Journal records every run record, every Confirmation and every automated step, each under its own actor. See Threads, Resolutions, the Journal and Signatures.
19 A Revision arrives.
Who: the QS; the Structural Engineer for the BBS.
The new sheet lies over the old, the changed Elements light up and their cost splits into quantity effect and price effect. No money carries across until the QS confirms every moved pair, and a signed BBS it touches goes stale. See Revision and one Revision through every role.
20 The site records what is built.
Who: the Site Engineer.
Element states are recorded, a pour’s Hold Points clear before its Pour Release is signed, and As built Records land on Elements, a Deviation shown beside its design value.
21 Bills are checked against what is built.
Who: the QS and the MD.
Each bill’s claim is checked against the Elements that support it; a claim is certified only up to what the Building shows, and a person signs it. Variations are priced; cash and Earned Value are read from the model.
22 Outsiders watch, never the money.
Who: Guests.
Buyers follow progress by Construction Stage; the Bank engineer and the Land-owner’s engineer see quantities only. Guests never see money, in any view, drawer, tooltip or export. See Roles and views.
Hand over the record with the keys
23 Handover.
Who: the Developer.
The Live Model goes with the Building: each Element carries what was designed, what was built and any Deviation, with who recorded it and when. In the research’s scale, what is handed over is a Level 1 digital model (Dong & Moshood, Buildings (MDPI), 2026): the record of the building, before its own data feeds it. See Handover.
24 The Digital Twin.
Who: the facility team.
As maintained Records land on the same Elements. Once the building’s own data flows back into it, the Live Model becomes the building’s Digital Twin: every asset keeps its identity from the drawing and its history. See the Digital Twin.

Level 1 → 2 → 3
Level 1: a digital model. Level 3: a twin, with automatic two-way data flow.
Questions
How does Vextrus turn 2D drawings into a Live Model?
The QS uploads the whole Drawing Set once and every sheet is accounted for. The QS confirms the set's conventions on a few one-click convention cards, and the machine drafts the model, every Element with its Trace and Measurement Lines. The QS then verifies it by exception, type by type, with four safeguards. Only confirmed Elements enter the Live Model.
What does the QS do in Vextrus?
The QS is the first daily user. The QS confirms the set's conventions, verifies the drafted model by exception, rules once per issue type, prices the Priced BOQ and issues the Estimate with a Signature. Under the done-for-you service, Vextrus's own QSs run the Takeoff, and a named Vextrus QS signs the Issued Estimate.
What happens when the drawings change?
Vextrus lays the new sheet over the old, lights every changed Element in 3D and splits the cost of the change into quantity effect and price effect. No money carries across the Revision until the QS confirms every moved pair, and every module shows Revision pending until it is resolved. A signed BBS the Revision touches goes stale.
What happens at handover?
At handover the Live Model goes with the Building: one database for its whole life, each Element carrying what was designed, what was built and any Deviation, with who recorded it and when. The record goes with the keys, not in a binder. Once the building's own data flows back into it, the Live Model becomes the building's Digital Twin.