What is a BOQ (bill of quantities)?
A BOQ, or bill of quantities, lists every item of work in a building with its quantity and unit. What it holds, who makes it, and what Vextrus adds.
To prepare a BOQ from 2D drawings, a QS measures each Element on the sheets as No. × L × B × H, totals the lines into BOQ Items and prices each item from its Rate Analysis. Vextrus keeps that method: the machine drafts the model from the whole Drawing Set, and the QS verifies it by exception.

You need the whole Drawing Set as the consultants issue it: every Discipline, every sheet at its current Revision, and the general notes. In Dhaka practice the latest Revision is the instruction, so a BOQ measured from a superseded sheet is measured from the wrong building. You also need the rules you measure by.
Those rules are the Measurement Rules: what is deducted, how laps and overlaps are taken, how each quantity is rounded. In Vextrus they form the Developer’s Rule Set, a copy of the Bangladeshi default set based on PWD practice, edited to the Developer’s own habits. One rule, as a QS reads it: deduct openings over 0.1 m² from brickwork.
A BOQ is prepared from drawings in seven steps: account for every sheet, read the frame of the building, measure each Element in building order, write each measurement as a line, total the lines into BOQ Items, price each item from its Rate Analysis, and add the layers that turn the priced bill into the Estimate.
List each sheet with its Revision and check the list both ways against the consultant’s drawing list, so nothing is measured twice or missed.
The general notes, the storeys and levels, and the grid. Every height and every position hangs on them.
Earthwork and filling; piles or a mat, pile caps and tie beams; columns and walls; beams; slabs; then masonry, finishes, doors and windows, services and external works.
No. × L × B × H, the quantity in its unit, the deductions named. This is the measurement sheet, and it is what lets anyone re-check the work.
Each item in its unit, in its BOQ Section, with its description, Mix and grade.
Its rate comes from its Rate Analysis: the Resources it consumes per unit, at your Market Prices.
The Priced BOQ’s direct cost, plus preliminaries and site overheads, contingency and taxes.
Concrete is measured as volume: for each Element, the number of like pieces times its length, breadth and depth, in cft for RCC. A column is measured storey by storey, a beam between its supports, a slab panel by its outline and thickness. Where a beam meets a slab, a rule decides which one owns the overlap.
The overlap matters because it is easy to count twice. In Vextrus the slab-beam overlap is an explicit, visible parameter of the Rule Set, and so is every other assumption a quantity rests on. The BOQ Item’s description names its Mix, such as RCC 1:1.5:3, and the Rate Analysis turns that Mix into cement, sand and stone chips. Wastage is not added to the measured quantity: it enters the Material Schedule, the list of what to buy. How a Rate Analysis works has its own article.
The Measurement Line
The figure is this plan’s own arithmetic.
In Excel, a BOQ is usually built from linked sheets: a measurement sheet with one row per line (No., L, B, H, quantity), an abstract that totals the lines into items, a rate analysis sheet, and the BOQ, where each quantity is multiplied by its rate. Excel holds the arithmetic well; nothing in a cell points back to the drawing.
That is the gap. When a figure is questioned, it is defended by rebuilding it from the tabs. When a Revision arrives, someone has to find what moved on the sheets and re-key every row it touches. Vextrus keeps Excel as a way out rather than the place the work lives: the Priced BOQ exports to Excel with live formulas, so change a quantity or a rate in the workbook and the workbook’s own Estimate follows, while the Live Model and its Traces stay in Vextrus. Its columns are added and removed as in Excel. See the Priced BOQ and its exports.
Vextrus prepares a BOQ from 2D drawings with the same method in different hands. The QS uploads the whole Drawing Set once, the consultants’ 2D DWG drawings as issued; the QS confirms a few one-click convention cards; the machine drafts every Element with its Measurement Lines; and the QS verifies the draft by exception on the drawing.
The detail follows the steps above.
Nobody redraws the building in 3D first. Only confirmed Elements count, and each quantity in the Priced BOQ keeps its measurement sheet, No. × L × B × H with the deductions named, each line opening its place on the drawing. See the Takeoff in Vextrus or the whole workflow, from the drawing set onwards.
See every article on the Learn page, and the terms in the glossary.
In building order, the way it is built: the grid and storeys first, then earthwork and filling, piles or a mat with their pile caps and tie beams, columns and walls, beams and slabs, then masonry, finishes, doors and windows, services and external works. Vextrus reviews the drafted model in building order too, type by type, so each type is settled before the next one rests on it.
A deduction is a Measurement Line of its own, named, such as an opening taken out of a wall's brickwork. The Rule Set says which deductions apply, for example: deduct openings over 0.1 m² from brickwork. In Vextrus every deduction appears on the measurement sheet under the quantity it reduces, and its line opens its place on the drawing.
Not in full. Every Discipline enters the Priced BOQ from its own drawings, never as an allowance: the structure from the structural drawings; electrical by the Point; plumbing and fire fixtures and equipment counted, their runs priced by rule per point and per fixture, the rule named. Vextrus reads each Discipline into its own part of one Live Model. A Discipline with no drawings becomes a Question, never a zero.
A BOQ, or bill of quantities, lists every item of work in a building with its quantity and unit. What it holds, who makes it, and what Vextrus adds.
A QS, the quantity surveyor or estimation engineer, measures a building's quantities from drawings and prices them. The work, and what changes in Vextrus.
Quantity takeoff measures every item of a building from its drawings. Manual and digital takeoff, the method, and how Vextrus keeps the QS in charge.
Drawn once. Every number traced.