What is a BOQ (bill of quantities)?
A BOQ, or bill of quantities, lists every item of work in a building with its quantity and unit. What it holds, who makes it, and what Vextrus adds.
A Rate Analysis breaks a BOQ Item into the Resources it consumes per unit, priced at the Developer’s Market Prices; that gives the working rate. The PWD Schedule of Rates gives a benchmark. Vextrus shows the PWD rate as printed and net of PWD’s mark-ups beside each working rate, and a gap between them is a question the QS answers.

A Rate Analysis is the breakdown of one BOQ Item into the Resources it consumes per unit of the item: the materials, the labour and any plant. Each Resource has a unit and a price. The quantities times the prices, added up, give the item’s working rate, and the same quantities, summed over the building, give the Material Schedule.
That second use is why a Rate Analysis matters beyond the price. It says what one cft of RCC or one sft of plaster takes, so it also says how many bags of cement, how much sand and how many bricks the whole building takes. In Vextrus every working rate comes from its Rate Analysis, at the Developer’s own Market Prices.
A rate analysis for concrete starts from the item and its unit, such as RCC 1:1.5:3 per cft. The Mix sets the share of cement, sand and stone chips; its dry-volume factor turns one cft of wet concrete into the dry materials it needs. Each material gets its Wastage, then its Market Price.
In steps:
Its description, its Mix and grade, and its unit.
Cement in bags, sand and stone chips by volume, worked from the Mix.
An allowance on each Resource for cutting, breakage and spillage. It enters the Material Schedule, what to buy; the BOQ quantity stays measured net.
On a self-executed Dhaka building, the labour is its own Labour Contract item, so the concrete rate covers materials only and its description says so.
Each Resource at the Developer’s Market Price; the sum is the working rate.
Worked through for 100 cft of RCC 1:1.5:3, as a synthetic example of the arithmetic: the dry volume is 150 cft (a dry-volume factor of 1.5; some QSs use 1.54), and the Mix’s 5.5 parts give cement 27.3 cft, about 21.8 bags at 1.25 cft a bag, sand 40.9 cft and stone chips 81.8 cft. Each then takes its Wastage, and each is priced at your Market Prices.
The labour rate goes in a Labour Contract: the Developer’s agreement with a labour-only contractor, priced per unit of its own scope. It is its own BOQ Item, per cft of RCC, per sft of plaster, or per sft of casting area covering Rebar binding, shuttering and casting together, and each item it covers takes no other labour.
Kept this way, nothing is paid twice. An RCC rate that covers materials only reads as what it is, and the casting labour sits once, in its own item. Where a trade is given out with its materials, one rate per unit covers both, and those materials stay out of the Developer’s own Material Schedule.
The PWD Schedule of Rates is the Public Works Department’s published book of rates for public works in Bangladesh: each item with its description, its unit and its rate, grouped into chapters by trade. Its printed rates carry PWD’s mark-ups for profit, overhead and VAT.
For a Developer’s QS it is a shared reference. In Vextrus each working rate comes from its Rate Analysis at the Developer’s own Market Prices, and the labour from the Developer’s own Labour Contracts, so the schedule is a benchmark to read a working rate against, not the rate itself.
Vextrus shows the PWD rate as the Benchmark Rate: the PWD Schedule of Rates rate for the item, as printed and net of PWD’s mark-ups (profit, overhead and VAT), set beside the working rate. It is never the rate the Priced BOQ is totalled on.
A printed PWD rate carries PWD’s mark-ups, so the Benchmark Rate is shown net of them as well as printed. Read beside the working rate, item by item, a gap between the two is a question the QS answers, labour included. The Priced BOQ also prints in a PWD-style layout, in ৳ grouped in lakh and crore. See the Priced BOQ, and the Market data Vextrus holds for Bangladesh.
Vextrus keeps rates current through the Market Price: the Developer’s price for one unit of a Resource on a date, the one place a price is changed. Change cement’s price once, and every working rate that uses cement, every amount and the Estimate follow, right through to the Excel export.
The prices are kept in dated sets, so the history stays readable. An Issued Estimate keeps the set it was issued on, frozen by a Signature with its issue number and date, and later figures are compared against it. Every assumption behind a rate, such as Wastage, is a visible parameter, so a QS can say why a rate is what it is. Read what a BOQ holds, or how its quantities are measured.
See every article on the Learn page, and the terms in the glossary, including Benchmark Rate and Market Price.
A Market Price is the Developer's price for one unit of a Resource on a date, kept in dated sets. It is the one place a price is changed in Vextrus: every working rate and amount that uses the Resource follows, while each Issued Estimate keeps the set of prices it was issued on.
A Benchmark Rate is the PWD Schedule of Rates rate for an item, shown in Vextrus beside the working rate, as printed and net of PWD's mark-ups (profit, overhead and VAT); a gap between them is a question the QS answers, labour included. It is a reference for the QS and the MD, never the rate the Priced BOQ is totalled on.
A Resource is what a BOQ Item consumes: a material such as cement, Rebar, sand, stone chips or bricks, a Labour Contract item, or a piece of plant, each with its unit and its Market Price. A Rate Analysis lists the Resources one unit of the item consumes; priced, they give its working rate.
Nothing changes in it. An Issued Estimate is frozen with the Market Prices it was issued on, by a Signature, with an issue number and date. The working Priced BOQ follows the new price, and later changes are compared against the Issued Estimate, so the MD sees what moved since the figure went to the board.
A BOQ, or bill of quantities, lists every item of work in a building with its quantity and unit. What it holds, who makes it, and what Vextrus adds.
How a QS prepares a BOQ from 2D drawings: measure each Element as No. × L × B × H, total the lines into BOQ Items, price each item. Then the Vextrus way.
A building's cost is decided by its own quantities and the prices paid for them. What drives it, and why a figure per sft is an average, not your building.